THEY WERE WITHOUT WATER. NOW, THE TAPS ARE BEGINNING TO RUN AGAIN. 
 
For a family that has lived with a dry tap, there is no progress report more powerful than seeing water flow again.
This week, Executive Mayor Cllr Mesuli Ngqondwana is on the ground, monitoring progress on bulk water provision initiatives across the O.R. Tambo District, checking what is working, confronting what is delaying delivery and pushing interventions towards completion.
We started at Ngqongweni Water Treatment Plant.
The plant is still undergoing rehabilitation, but the work is already making a difference. It has been partially refurbished and restored to operation, currently producing approximately 0.35 megalitres of water per day.
 
Already, communities in Ntsonyeni 1, 2 and 3 and Ngqongweni are receiving potable water again.
For those households, 0.35 ML/day is not just a technical figure. It is a tap running again. It is relief. It is hope returning.
But progress is not completion.
The contractor remains on site. Rehabilitation continues. Outstanding challenges are being addressed, including work towards restoring supply to NoHokoza and Nodushe as the plant moves towards its full 1.1 ML/day capacity.
The Mayor is not on the ground to celebrate an unfinished job. He is there to make sure the work does not stop until progress at the plant translates into water for every community that depends on it.
The water is beginning to flow again. The work continues. Hope is returning, one tap at a time.